(i)
describe—
(I)
how the positive train control system will provide for interoperability of the system with the movements of trains of other railroad carriers over its lines; and
(II)
how, to the extent practical, the positive train control system will be implemented in a manner that addresses areas of greater risk before areas of lesser risk;
(iii)
provide—
(I)
the calendar year or years in which spectrum will be acquired and will be available for use in each area as needed for positive train control system implementation, if such spectrum is not already acquired and available for use;
(II)
the total amount of positive train control system hardware that will be installed for implementation, with totals separated by each major hardware category;
(III)
the total amount of positive train control system hardware that will be installed by the end of each calendar year until the positive train control system is implemented, with totals separated by each hardware category;
(IV)
the total number of employees required to receive training under the applicable positive train control system regulations;
(V)
the total number of employees that will receive the training, as required under the applicable positive train control system regulations, by the end of each calendar year until the positive train control system is implemented;
(VI)
a summary of any remaining technical, programmatic, operational, or other challenges to the implementation of a positive train control system, including challenges with—
(aa)
availability of public funding;
(bb)
interoperability;
(cc)
spectrum;
(dd)
software;
(ee)
permitting; and
(ff)
testing, demonstration, and certification; and
(VII)
a schedule and sequence for implementing a positive train control system by the deadline established under paragraph (1).