§ 806.
Time limit for construction of project works; extension of time; termination or revocation of licenses for delay

The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall within the time fixed in the license complete and put into operation such part of the ultimate development as the commission shall deem necessary to supply the reasonable needs of the then available market, and shall from time to time thereafter construct such

(June 10, 1920, ch. 285, pt. I, § 13, 41 Stat. 1071; renumbered pt. I, Aug. 26, 1935, ch. 687, title II, § 212, 49 Stat. 847; amended Pub. L. 115–270, title III, § 3001(b), Oct. 23, 2018, 132 Stat. 3862.)