Any order or decision issued by the Secretary in a civil penalty proceeding or any other proceeding required to be conducted pursuant to
section 554 of title 5 shall be subject to judicial review on or before 30 days from the date of such order or decision in accordance with subsection (b) of this section in the United States District Court for the district in which the surface coal mining operation is located. In the case of a proceeding to review an order or decision issued by the Secretary under the penalty section of this chapter, the court shall have jurisdiction to enter an order requiring payment of any civil penalty assessment enforced by its judgment. This availability of review established in this subsection shall not be construed to limit the operations of rights established in
section 1270 of this title.