U.S Code last checked for updates: Nov 26, 2024
§ 1283.
Plans, specifications, estimates, and payments
(a)
Submission; contractual nature of approval by Administrator; agreement on eligible costs; single grant
(1)
Each applicant for a grant shall submit to the Administrator for his approval, plans, specifications, and estimates for each proposed project for the construction of treatment works for which a grant is applied for under section 1281(g)(1) of this title from funds allotted to the State under section 1285 of this title and which otherwise meets the requirements of this chapter. The Administrator shall act upon such plans, specifications, and estimates as soon as practicable after the same have been submitted, and his approval of any such plans, specifications, and estimates shall be deemed a contractual obligation of the United States for the payment of its proportional contribution to such project.
(2)
Agreement on eligible costs.—
(A)
Limitation on modifications.—
Before taking final action on any plans, specifications, and estimates submitted under this subsection after the 60th day following February 4, 1987, the Administrator shall enter into a written agreement with the applicant which establishes and specifies which items of the proposed project are eligible for Federal payments under this section. The Administrator may not later modify such eligibility determinations unless they are found to have been made in violation of applicable Federal statutes and regulations.
(B)
Limitation on effect.—
Eligibility determinations under this paragraph shall not preclude the Administrator from auditing a project pursuant to section 1361 of this title, or other authority, or from withholding or recovering Federal funds for costs which are found to be unreasonable, unsupported by adequate documentation, or otherwise unallowable under applicable Federal cost principles, or which are incurred on a project which fails to meet the design specifications or effluent limitations contained in the grant agreement and permit pursuant to section 1342 of this title for such project.
(3)
In the case of a treatment works that has an estimated total cost of $8,000,000 or less (as determined by the Administrator), and the population of the applicant municipality is twenty-five thousand or less (according to the most recent United States census), upon completion of an approved facility plan, a single grant may be awarded for the combined Federal share of the cost of preparing construction plans and specifications, and the building and erection of the treatment works.
(b)
Periodic payments
(c)
Final payments
(d)
Projects eligible
(e)
Technical and legal assistance in administration and enforcement of contracts; intervention in civil actions
(f)
Design/build projects
(1)
Agreement
(2)
Limitation on projects
Agreements under this subsection shall be limited to projects under an approved facility plan which projects are—
(A)
treatment works that have an estimated total cost of $8,000,000 or less; and
(B)
any of the following types of waste water treatment systems: aerated lagoons, trickling filters, stabilization ponds, land application systems, sand filters, and subsurface disposal systems.
(3)
Required terms
An agreement entered into under this subsection shall—
(A)
set forth an amount agreed to as the maximum Federal contribution to the project, based upon a competitively bid document of basic design data and applicable standard construction specifications and a determination of the federally eligible costs of the project at the applicable Federal share under section 1282 of this title;
(B)
set forth dates for the start and completion of construction of the treatment works by the applicant and a schedule of payments of the Federal contribution to the project;
(C)
contain assurances by the applicant that (i) engineering and management assistance will be provided to manage the project; (ii) the proposed treatment works will be an operable unit and will meet all the requirements of this subchapter; and (iii) not later than 1 year after the date specified as the date of completion of construction of the treatment works, the treatment works will be operating so as to meet the requirements of any applicable permit for such treatment works under section 1342 of this title;
(D)
require the applicant to obtain a bond from the contractor in an amount determined necessary by the Administrator to protect the Federal interest in the project; and
(E)
contain such other terms and conditions as are necessary to assure compliance with this subchapter (except as provided in paragraph (4) of this subsection).
(4)
Limitation on application
(5)
Reservation to assure compliance
(6)
Limitation on obligations
(7)
Allowance
(8)
Limitation on Federal contributions
(9)
Recovery action
(10)
Prevention of double benefits
(June 30, 1948, ch. 758, title II, § 203, as added Pub. L. 92–500, § 2, Oct. 18, 1972, 86 Stat. 835; amended Pub. L. 93–243, § 2, Jan. 2, 1974, 87 Stat. 1069; Pub. L. 95–217, §§ 18, 19, Dec. 27, 1977, 91 Stat. 1571, 1572; Pub. L. 96–483, § 6, Oct. 21, 1980, 94 Stat. 2362; Pub. L. 97–117, § 9, Dec. 29, 1981, 95 Stat. 1626; Pub. L. 100–4, title II, §§ 203, 204, Feb. 4, 1987, 101 Stat. 16, 17.)