(a) The compliance schedule for the source identified below is approved as a revision to the plan pursuant to § 51.104 and subpart N of this chapter. All regulations cited are air pollution control regulations of the State, unless otherwise noted.

Missouri

Source Location Regulation involved Adopted date Effective date Final compliance date
Pilot Knob Pelleting CoPilot Knob, MOV(10 CSR 10-3.050)Oct. 19, 1977ImmediatelyDec. 31, 1982.
Union Electric Labadie power plantLabadie, MO10 CSR 10-5.090 and 10 CSR 10-5.030June 20, 1979July 20, 1979Mar. 1, 1984.
St. Joe Minerals Corp., Pea Ridge Iron Ore FacilityWashington County, MO10 CSR 10-3,050Mar. 23, 1983Mar. 23, 1983Dec. 31, 1988.
St. Joe Minerals Corp., Pea Ridge Iron Ore Facility......do......doApr. 22, 1981Dec. 28, 1981July 1, 1985.
Associated Electric Cooperative, Inc., Thomas Hill Power Plant—Unit 1Randolph County, MO10 CSR 10-3.060 and 10 CSR 10-3.080June 17, 1981Jan. 12, 1982June 1, 1984.
American Oil Co. (AMOCO)Sugar Creek, MO10 CSR 10-2.260Feb. 18, 1981Oct. 1, 1981June 1, 1982.
St. Joe Lead CoHerculaneum, MO§ 203.050.1(5) RSM01978Aug. 15, 1980ImmediatelyOct. 27, 1984.
AMAX Lead CoBoss, MO......do......do......doApr. 27, 1985.

(b) The compliance schedule submitted for the source identified below is disapproved as not meeting the requirements of subpart N of this chapter. All regulations cited are air pollution control regulations of the State, unless otherwise noted.

Source Location Regulation involved Date adopted
Columbia Water & Light DepartmentColumbiaS-VIApr. 25, 1973.
Union Electric: Electric generating facilityLabadieXMar. 28, 1974.
DoPortage des SiouxXJuly 25, 1974.
International Multifoods Corp.: Mechanical siftersNorth Kansas City( 1)Aug. 31, 1976.
Meremac Mining Co., furnace and cooler Nos. 1 through 5Pea RidgeII (10 CSR 10-3.050)Feb. 23, 1977.
Empire District Electric Co., Power PlantAsbury JoplinIII (10 CSR 10-3.060) V (10 CSR 10-3.080)Apr. 27, 1977.
Missouri Portland Cement Co., clinker cooler No. 1Sugar CreekII (10 CSR 10-2.030) V (10 CSR 10-2.060)June 22, 1977.
Missouri Public Service Co., Sibley powerplant, unit Nos. 1, 2, and 3SibleyIII (10 CSR 10-2.040)June 26, 1977.
Tamko Asphalt Products, Inc., asphalt saturating lineJoplinV (10 CSR 10-3.080)July 26, 1977.
University of Missouri power plantColumbia10 CSR 10-3.060Feb. 21, 1979.
Noranda Aluminum, IncNew Madrid10 CSR 10-3.050Feb. 23, 1977.
Associated Electric Cooperative, Inc., Units 1 and 2......do110 CSR 10-3.060Apr. 18, 1979.

1 Regulation IV, air pollution control regulations for Kansas City metropolitan area.

Note: X = Air Pollution Control Regulations for the St. Louis Metropolitan Area.

[39 FR 30835, Aug. 26, 1974] Editorial Note:For Federal Register citations affecting § 52.1335, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.govinfo.gov.
authority: 42 U.S.C. 7401
cite as: 40 CFR 52.1335