Regulations last checked for updates: Nov 25, 2024

Title 30 - Mineral Resources last revised: Nov 19, 2024
§ 250.730 - What are the general requirements for BOP systems and system components?

(a) You must ensure that the BOP system and system components are designed, installed, maintained, inspected, tested, and used properly to ensure well control. The working-pressure rating of each BOP component (excluding annular(s)) must exceed MASP as defined for the operation. For a subsea BOP, the MASP must be determined at the mudline. The BOP system includes the BOP stack, control system, and any other associated system(s) and equipment. The BOP system and individual components must be able to perform their expected functions and be compatible with each other. Your BOP system must be capable of closing and sealing the wellbore to the well's MASP at all times, except as otherwise specified in the BOP system requirements of this subpart. The BOP system must be capable of closing and sealing without losing ram closure time and sealing integrity due to the corrosiveness, volume, and abrasiveness of any fluids in the wellbore that the BOP system may encounter. Your BOP system must meet the following requirements:

(1) The BOP requirements of API Standard 53 (incorporated by reference in § 250.198) and the requirements of §§ 250.733 through 250.739. If there is a conflict between API Standard 53 and the requirements of this subpart, you must follow the requirements of this subpart.

(2) The provisions of the following industry standards (all incorporated by reference in § 250.198) that apply to BOP systems:

(i) ANSI/API Spec. 6A;

(ii) ANSI/API Spec. 16A;

(iii) ANSI/API Spec. 16C;

(iv) API Spec. 16D; and

(v) ANSI/API Spec. 17D.

(3) For surface and subsea BOPs, the pipe and variable bore rams installed in the BOP stack must be capable of effectively closing and sealing on the tubular body of any drill pipe, workstring, and tubing (excluding tubing with exterior control lines and flat packs) in the hole under MASP, as defined for the operation, at the proposed regulator settings of the BOP control system.

(4) The current set of approved schematic drawings must be available on the rig and at an onshore location. If you make any modifications to the BOP or control system that will require changes to your BSEE-approved schematic drawings, you must suspend operations until you obtain approval from the District Manager.

(b) You must ensure that the design, fabrication, maintenance, and repair of your BOP system is in accordance with the requirements contained in this part, applicable Original Equipment Manufacturer's (OEM) recommendations unless otherwise directed by BSEE, and recognized engineering practices. The training and qualification of repair and maintenance personnel must meet or exceed applicable OEM training recommendations unless otherwise directed by BSEE.

(c) You must follow the failure reporting procedures contained in API Standard 53 (incorporated by reference in § 250.198) and:

(1) You must provide a written notice of equipment failure to the Office of Offshore Regulatory Programs (OORP) Chief, any third party designated by BSEE pursuant to paragraph (c)(4) of this section, and the manufacturer of such equipment within 30 days after the discovery and identification of the failure. A failure is any condition that prevents the equipment from meeting the functional specification.

(2) You must start an investigation and a failure analysis within 90 days of the failure to determine the cause of the failure and complete the investigation and the failure analysis within 120 days after initiation. You also must document the results and any corrective action. You must submit the analysis report to the OORP Chief, any third party designated by BSEE pursuant to paragraph (c)(4) of this section, and the manufacturer. If you cannot complete the investigation and analysis within the specified time, you must submit an extension request detailing when and how you will complete the investigation and analysis to BSEE for approval. You must submit the extension request to the OORP Chief.

(3) If the equipment manufacturer notifies you that it has changed the design of the equipment that failed or if you have changed operating or repair procedures as a result of a failure, then you must, within 30 days of such changes, report the design change or modified procedures in writing to the OORP Chief, and any third party designated by BSEE pursuant to paragraph (c)(4) of this section.

(4) Submit notices and reports to the Chief, Office of Offshore Regulatory Programs; Bureau of Safety and Environmental Enforcement; 45600 Woodland Road, Sterling, Virginia 20166. BSEE may designate a third party to also receive the data and reports. If BSEE designates a third party, you must submit the data and reports to the designated third party as well.

(d) If you plan to use a BOP stack manufactured after the effective date of this regulation, you must use one manufactured pursuant to an ANSI/API Spec. Q1 (as incorporated by reference in § 250.198) quality management system. Such quality management system must be certified by an entity that meets the requirements of ISO/IEC 17021-1 (as incorporated by reference in § 250.198).

(1) BSEE may consider accepting equipment manufactured under quality assurance programs other than ANSI/API Spec. Q1, provided you submit a request to the Chief, OORP for approval, containing relevant information about the alternative program.

(2) You must submit this request to the Chief, OORP; Bureau of Safety and Environmental Enforcement; 45600 Woodland Road, Sterling, Virginia 20166.

[84 FR 21977, May 15, 2019, as amended at 88 FR 58347, Aug. 23, 2023]
authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.730