For each . . .
| For which . . .
| You must . . .
| You must comply with the standard . . .
|
---|
1. Existing CEV at a major source facility | a. Not applicable | i. Continuously reduce EtO emissions by 99.94 percent
1 | No later than April 5, 2027.
|
2. Existing CEV at an area source facility | a. Facility EtO use is at least 60 tpy | i. Continuously reduce EtO emissions by 99.9 percent 1 2 | No later than April 6, 2026.
|
| b. Facility EtO use is less than 60 tpy | i. Continuously reduce EtO emissions by 99 percent 1 3 | No later than April 5, 2027.
|
3. New CEV at a major source facility | a. Initial startup is on or before April 5, 2024 | i. Continuously reduce EtO emissions by 99.94 percent
1 | No later than April 5, 2024.
|
| b. Initial startup is after April 5, 2024 | i. Continuously reduce EtO emissions by 99.94 percent
1 | Upon startup of the source.
|
4. New CEV at an area source facility | a. Initial startup is on or before April 5, 2024, and facility EtO use is at least 60 tpy | i. Continuously reduce EtO emissions by 99.9 percent 1 4 | No later than April 5, 2024.
|
| b. Initial startup is on or before April 5, 2024, facility EtO use is less than 60 tpy | i. Continuously reduce EtO emissions by 99 percent 1 5 | No later than April 5, 2024.
|
| c. Initial startup is after April 5, 2024, and facility EtO use is at least 60 tpy | i. Continuously reduce EtO emissions by 99.9 percent 1 4 | Upon startup of the source.
|
| d. Initial startup is after April 5, 2024, facility EtO use is less than 60 tpy | i. Continuously reduce EtO emissions by 99 percent 1 5 | Upon startup of the source.
|