For each . . .
| For which . . .
| You must . . .
| You must comply with the requirement(s) . . .
|
---|
1. Existing collection of Group 2 room air emissions at a major source facility | a. Not applicable | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent
1 | No later than April 5, 2027.
|
2. Existing collection of Group 2 room air emissions at an area source facility | a. Facility EtO use is at least 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
2 Also,
ii. Continuously reduce EtO emissions by 98 percent
1
2 | No later than April 6, 2026.
|
| b. Facility EtO use is at least 4 tpy but less than 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
2 Also,
ii. Continuously reduce EtO emissions by 80 percent
1
2 | No later than April 6, 2026.
|
| c. Facility EtO use is less than 4 tpy | Lower the EtO concentration within each sterilization chamber to 1 ppm before the chamber can be opened
3 | No later than April 5, 2027.
|
3. New collection of Group 2 room air emissions at a major source facility | a. Initial startup is on or before April 5, 2024 | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent
1 | No later than April 5, 2024.
|
| b. Initial startup is after April 5, 2024 | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system. Also,
ii. Continuously reduce EtO emissions by 86 percent
1 | Upon startup of the source.
|
4. New collection of Group 2 room air emissions at an area source facility | a. Initial startup is on or before April 5, 2024, and facility EtO use is at least 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
5 Also,
ii. Continuously reduce EtO emissions by 98 percent
1
5 | No later than April 5, 2024.
|
| b. Initial startup is on or before April 5, 2024, and facility EtO use is less than 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
6 Also,
ii. Continuously reduce EtO emissions by 80 percent
1
6 | No later than April 5, 2024.
|
| c. Initial startup is after April 5, 2024, and facility EtO use is at least 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
5 Also,
ii. Continuously reduce EtO emissions by 98 percent
1
5 | Upon startup of the source.
|
| d. Initial startup is after April 5, 2024, and facility EtO use is less than 20 tpy | i. Operate all areas of the facility that contain Group 2 room air emissions with PTE, with all exhaust gas streams being captured and routed to a control system.
6 Also,
ii. Continuously reduce EtO emissions by 80 percent
1
6 | Upon startup of the source.
|