Citation
| Subject
| Applies to subpart UUUUU
|
---|
§ 63.1 | Applicability | Yes.
|
§ 63.2 | Definitions | Yes. Additional terms defined in § 63.10042.
|
§ 63.3 | Units and Abbreviations | Yes.
|
§ 63.4 | Prohibited Activities and Circumvention | Yes.
|
§ 63.5 | Preconstruction Review and Notification Requirements | Yes.
|
§ 63.6(a), (b)(1) through (5), (b)(7), (c), (f)(2) and (3), (h)(2) through (9), (i), (j) | Compliance with Standards and Maintenance Requirements | Yes.
|
§ 63.6(e)(1)(i) | General Duty to minimize emissions | No. See § 63.10000(b) for general duty requirement.
|
§ 63.6(e)(1)(ii) | Requirement to correct malfunctions ASAP | No.
|
§ 63.6(e)(3) | SSM Plan requirements | No.
|
§ 63.6(f)(1) | SSM exemption | No.
|
§ 63.6(h)(1) | SSM exemption | No.
|
§ 63.6(g) | Compliance with Standards and Maintenance Requirements, Use of an alternative non-opacity emission standard | Yes. See §§ 63.10011(g)(4) and 63.10021(h)(4) for additional requirements.
|
§ 63.7(e)(1) | Performance testing | No. See § 63.10007.
|
§ 63.8 | Monitoring Requirements | Yes.
|
§ 63.8(c)(1)(i) | General duty to minimize emissions and CMS operation | No. See § 63.10000(b) for general duty requirement.
|
§ 63.8(c)(1)(iii) | Requirement to develop SSM Plan for CMS | No.
|
§ 63.8(d)(3) | Written procedures for CMS | Yes, except for last sentence, which refers to an SSM plan. SSM plans are not required.
|
§ 63.9 | Notification Requirements | Yes, except (1) for the 60-day notification prior to conducting a performance test in § 63.9(e); instead use a 30-day notification period per § 63.10030(d), (2) the notification of the CMS performance evaluation in § 63.9(g)(1) is limited to RATAs, and (3) the information required per § 63.9(h)(2)(i); instead provide the applicable information in § 63.10030(e)(1) through (8), for the initial notification of compliance status, only.
|
§ 63.10(a), (b)(1), (c), (d)(1) and (2), (e), and (f) | Recordkeeping and Reporting Requirements | Yes, except for the requirements to submit written reports under § 63.10(e)(3)(v).
|
§ 63.10(b)(2)(i) | Recordkeeping of occurrence and duration of startups and shutdowns | No.
|
§ 63.10(b)(2)(ii) | Recordkeeping of malfunctions | No. See § 63.10001 for recordkeeping of (1) occurrence and duration and (2) actions taken during malfunction.
|
§ 63.10(b)(2)(iii) | Maintenance records | Yes.
|
§ 63.10(b)(2)(iv) | Actions taken to minimize emissions during SSM | No.
|
§ 63.10(b)(2)(v) | Actions taken to minimize emissions during SSM | No.
|
§ 63.10(b)(2)(vi) | Recordkeeping for CMS malfunctions | Yes.
|
§ 63.10(b)(2)(vii) through (ix) | Other CMS requirements | Yes.
|
§ 63.10(b)(3) and (d)(3) through (5) | | No.
|
§ 63.10(c)(7) | Additional recordkeeping requirements for CMS — identifying exceedances and excess emissions | Applies only through December 31, 2023.
|
§ 63.10(c)(8) | Additional recordkeeping requirements for CMS—identifying exceedances and excess emissions | Applies only through December 31, 2023.
|
§ 63.10(c)(10) | Recording nature and cause of malfunctions | No. See § 63.10032(g) and (h) for malfunctions recordkeeping requirements.
|
§ 63.10(c)(11) | Recording corrective actions | No. See § 63.10032(g) and (h) for malfunctions recordkeeping requirements.
|
§ 63.10(c)(15) | Use of SSM Plan | No.
|
§ 63.10(d)(5) | SSM reports | No. See § 63.10021(h) and (i) for malfunction reporting requirements.
|
§ 63.10(e)(3)(v) and (vi) | Excess emissions and CMS performance reports | Applies only through December 31, 2023.
|
§ 63.11 | Control Device Requirements | No.
|
§ 63.12 | State Authority and Delegation | Yes.
|
§§ 63.13 through 63.16 | Addresses, Incorporation by Reference, Availability of Information, Performance Track Provisions | Yes.
|
§§ 63.1(a)(5),(a)(7) through (9), (b)(2), (c)(3) and (4), (d), 63.6(b)(6), (c)(3) and (4), (d), (e)(2), (e)(3)(ii), (h)(3), (h)(5)(iv), 63.8(a)(3), 63.9(b)(3), (h)(4), 63.10(c)(2) through (4), (c)(9). | Reserved | No. |