Regulations last checked for updates: Nov 22, 2024

Title 40 - Protection of Environment last revised: Nov 20, 2024
Appendix - Table 1 to Subpart ZZZZZZ of Part 63—Applicability of General Provisions to Aluminum, Copper, and Other Nonferrous Foundries Area Sources

As required in § 63.11555, “What General Provisions apply to this subpart?,” you must comply with each requirement in the following table that applies to you.

Citation Subject Applies to subpart ZZZZZZ? Explanation
§ 63.1(a)(1), (a)(2), (a)(3), (a)(4), (a)(6), (a)(10)-(a)(12), (b)(1), (b)(3), (c)(1), (c)(2), (c)(5), (e)ApplicabilityYes§ 63.11544(f) exempts affected sources from the obligation to obtain a title V operating permit.
§ 63.1(a)(5), (a)(7)-(a)(9), (b)(2), (c)(3), (c)(4), (d)ReservedNo
§ 63.2DefinitionsYes
§ 63.3Units and AbbreviationsYes
§ 63.4Prohibited Activities and CircumventionYes
§ 63.5Preconstruction Review and Notification RequirementsYes
§ 63.6(a), (b)(1)-(b)(5), (b)(7), (c)(1), (c)(2), (c)(5), (e)(1), (e)(3)(i), (e)(3)(iii)-(e)(3)(ix), (f)(2), (f)(3), (g), (i), (j)Compliance with Standards and Maintenance RequirementsYes
§ 63.6(f)(1)Compliance with Nonopacity Emission StandardsNoSubpart ZZZZZZ requires continuous compliance with all requirements in this subpart.
§ 63.6(h)(1), (h)(2), (h)(5)-(h)(9)Compliance with Opacity and Visible Emission LimitsNoSubpart ZZZZZZ does not contain opacity or visible emission limits.
§ 63.6(b)(6), (c)(3), (c)(4), (d), (e)(2), (e)(3)(ii), (h)(3), (h)(5)(iv)ReservedNo
§ 63.7Applicability and Performance Test DatesYes
§ 63.8(a)(1), (b)(1), (f)(1)-(5), (g)Monitoring RequirementsYes
§ 63.8(a)(2), (a)(4), (b)(2)-(3), (c), (d), (e), (f)(6), (g)Continuous Monitoring SystemsNoSubpart ZZZZZZ does not require a flare or CPMS, COMS or CEMS.
§ 63.8(a)(3)[Reserved]No
§ 63.9(a), (b)(1), (b)(2)(i)-(iii), (b)(5), (c), (d), (e), (h)(1)-(h)(3), (h)(5), (h)(6), (j)Notification RequirementsYesSubpart ZZZZZZ requires submission of Notification of Compliance Status within 120 days of compliance date unless a performance test is required.
§ 63.9(b)(2)(iv)-(v), (b)(4), (f), (g), (i)No
§ 63.9(b)(3), (h)(4)ReservedNo
§ 63.10(a), (b)(1), (b)(2)(i)-(v), (vii), (vii)(C), (viii), (ix), (b)(3), (d)(1)-(2), (d)(4), (d)(5), (f)Recordkeeping and Reporting RequirementsYes
§ 63.10(b)(2)(vi), (b)(2)(vii)(A)-(B), (c), (d)(3), (e)NoSubpart ZZZZZZ does not require a CPMS, COMS, CEMS, or opacity or visible emissions limit.
§ 63.10(c)(2)-(c)(4), (c)(9)ReservedNo
§ 63.11Control Device RequirementsNo
§ 63.12State Authority and DelegationsYes
§§ 63.13-63.16Addresses, Incorporations by Reference, Availability of Information, Performance Track ProvisionsYes
authority: 42 U.S.C. 7401