§ 57.705 - Contents of SIP Compliance Schedule required by (2) and (3).

This section applies to smelters which are required to submit a SIP Compliance Schedule as discussed below.

(a) Each SIP Compliance Schedule required by § 57.201(d) (2) and (3) must contain the following elements:

(1) Description of the overall design of the SO2 control system(s) to be installed;

(2) Descriptions of specific process hardware to be used in achieving compliance with the SIP emission limitation including gas capacity values;

(3) The date by which contracts will be let or purchase orders issued to accomplish any necessary performance improvements;

(4) The date for initiating on-site construction or installation of necessary equipment;

(5) The date by which on-site construction or installation of equipment is to be completed;

(6) The date for achievement of final compliance with SIP emission limitations; and

(7) Any other measures necessary to assure compliance with all SIP requirements as expeditiously as practicable.

(b) Operations of SCS. Smelters to which § 57.705 is applicable must comply with all elements of § 57.703.

authority: Secs. 110, 114, 119, 301, Clean Air Act, as amended (42 U.S.C. 7410,7414,7419,and; sec. 406 of Pub. L. 95-95
source: 50 FR 6448, Feb. 15, 1985, unless otherwise noted.
cite as: 40 CFR 57.705