Appendix - Table 8 to Subpart PPP of Part 63—Routine Reports Required by This Subpart
Reference Description of report Due date
§ 63.1439(b) and subpart A of this partRefer to § 63.1439(b), Table 1 of this subpart, and to subpart A of this partRefer to subpart A of this part.
§ 63.1439(e)(3)Initial notificationNew affected sources w/ initial start-up at least 90 days after June 1, 1999: submit the application for approval of construction or reconstruction in lieu of the initial notification report.
New affected sources w/ initial start-up prior to 90 days after June 1, 1999:by 90 days after June 1, 1999.
§ 63.1439(e)(4)Precompliance Report aExisting affected sources: 12 months prior to compliance date.
New affected sources: with the application for approval of construction or reconstruction.
§ 63.1439(e)(5)Notification of Compliance Status bWithin 150 days after the compliance date.
§ 63.1439(e)(6)Periodic ReportsSemiannually, no later than 60 days after the end of each 6-month period. See § 63.1439(e)(6)(i) for the due date for this report.
§ 63.1439(e)(6)(iii)Quarterly reports for sources with excursions (upon request of the Administrator)No later than 60 days after the end of each quarter.
§ 63.506(e)(7)(i)Storage Vessels Notification of InspectionAt least 30 days prior to the refilling of each storage vessel or the inspection of each storage vessel.

a There may be two versions of this report due at different times; one for equipment subject to § 63.1434 and one for other emission points subject to this subpart.

b There will be two versions of this report due at different times; one for equipment subject to § 63.1434 and one for other emission points subject to this subpart.

[65 FR 26506, May 8, 2000]
authority: 42 U.S.C. 7401