Regulations last checked for updates: Nov 22, 2024

Title 40 - Protection of Environment last revised: Nov 20, 2024
Appendix - Table 7 to Subpart VVVV of Part 63—Applicability and Timing of Notifications

As specified in § 63.5761(a), you must submit notifications according to the following table:

If your facility— You must submit— By this date—
1. Is an existing source subject to this subpartAn initial notification containing the information specified in § 63.9(b)(2)No later than the dates specified in § 63.9(b)(2).
2. Is a new source subject to this subpartThe notifications specified in § 63.9(b) (3) to (5)No later than the dates specified § 63.9(b)(4) and (5).
3. Qualifies for a compliance extension as specified in § 63.9(c)A request for a compliance extension as specified in § 63.9(c)No later than the dates specified in § 63.6(i).
4. Is complying with organic HAP content limits, application equipment requirements; or MACT model point value averaging provisionsA notification of compliance status as specified in § 63.9(h)No later than 30 calendar days after the end of the first 12-month averaging period after your facility's compliance date.
5. Is complying by using an add-on control devicea. notification of intent to conduct a performance test as specified in § 63.9(e)No later than the date specified in § 63.9(e).
b. A notification of the date for the continuous monitoring system performance evaluation as specified in § 63.9(g)With the notification of intent to conduct a performance test.
c. A notification of compliance status as specified in § 63.9(h)No later than 60 calendar days after the completion of the add-on control device performance test and continuous monitoring system performance evaluation.
authority: 42 U.S.C. 7401
source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.