Regulations last checked for updates: Nov 22, 2024

Title 40 - Protection of Environment last revised: Nov 20, 2024
Appendix - Table 10 to Subpart HHHHH of Part 63—Applicability of General Provisions to This Subpart

As specified in § 63.8095, the parts of the general provisions that apply to you are shown in the following table:

Table 10 to Subpart HHHHH of Part 63—Applicability of General Provisions to This Subpart

Citation Subject Explanation
§ 63.1ApplicabilityYes.
§ 63.2DefinitionsYes.
§ 63.3Units and AbbreviationsYes.
§ 63.4Prohibited ActivitiesYes.
§ 63.5Construction/ReconstructionYes.
§ 63.6(a)ApplicabilityYes.
§ 63.6(b)(1)-(4)Compliance Dates for New and Reconstructed sourcesYes.
§ 63.6(b)(5)NotificationYes.
§ 63.6(b)(6)[Reserved]
§ 63.6(b)(7)Compliance Dates for New and Reconstructed Area Sources That Become MajorYes.
§ 63.6(c)(1)-(2)Compliance Dates for Existing SourcesYes.
§ 63.6(c)(3)-(4)[Reserved]
§ 63.6(c)(5)Compliance Dates for Existing Area Sources That Become MajorYes.
§ 63.6(d)[Reserved]
§ 63.6(e)(1)(i)General Duty to Minimize EmissionsYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(e) for the general duty requirement.
§ 63.6(e)(1)(ii)Requirement to Correct Malfunctions as Soon as PossibleYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
§ 63.6(e)(1)(iii)-(2)Operation and MaintenanceYes.
§ 63.6(e)(3)SSM PlanYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
§ 63.6(f)(1)Compliance with Non-Opacity Standards Except During SSMNo. See § 63.8000(a).
§ 63.6(f)(2)-(3)Methods for Determining ComplianceYes.
§ 63.6(g)(1)-(3)Alternative StandardYes.
§ 63.6(h)(1)Compliance with Opacity/Visible Emission (VE) Standards Except During SSMNo. See § 63.8000(a).
§ 63.6(h)(2)-(9)Opacity/VE StandardsOnly for flares for which Method 22 of 40 CFR part 60, appendix A-7, observations are required as part of a flare compliance assessment.
§ 63.6(i)(1)-(14)Compliance ExtensionYes.
§ 63.6(j)Presidential Compliance ExemptionYes.
§ 63.7(a)(1)-(2)Performance Test DatesYes, except substitute 150 days for 180 days.
§ 63.7(a)(3)-(4)CAA Section 114 Authority, Force MajeureYes, and these paragraphs also apply to flare compliance assessments as specified under § 63.997(b)(2).
§ 63.7(b)(1)Notification of Performance TestYes.
§ 63.7(b)(2)Notification of ReschedulingYes.
§ 63.7(c)Quality Assurance/Test PlanYes, except the test plan must be submitted with the notification of the performance test if the control device controls process vessels.
§ 63.7(d)Testing FacilitiesYes.
§ 63.7(e)(1)Conditions for Conducting Performance TestsYes, before the compliance date specified in § 63.7995(e), except that performance tests for process vessels must be conducted under worst-case conditions as specified in § 63.8005. No, on and after the compliance date specified in § 63.7995(e). See § 63.8005(d).
§ 63.7(e)(2)Conditions for Conducting Performance TestsYes.
§ 63.7(e)(3)Test Run DurationYes.
§ 63.7(f)Alternative Test MethodYes.
§ 63.7(g)Performance Test Data AnalysisYes.
§ 63.7(h)Waiver of TestsYes.
§ 63.8(a)(1)Applicability of Monitoring RequirementsYes.
§ 63.8(a)(2)Performance SpecificationsYes.
§ 63.8(a)(3)[Reserved]
§ 63.8(a)(4)Monitoring with FlaresYes.
§ 63.8(b)(1)MonitoringYes.
§ 63.8(b)(2)-(3)Multiple Effluents and Multiple Monitoring SystemsYes.
§ 63.8(c)(1)Monitoring System Operation and MaintenanceYes.
§ 63.8(c)(1)(i)Maintain and operate CMSYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(e) for the general duty to maintain and operate each CMS.
§ 63.8(c)(1)(ii)Routine repairsYes.
§ 63.8(c)(1)(iii)Requirement to develop SSM plan for CMSYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
§ 63.8(c)(2)-(3)Monitoring System InstallationYes.
§ 63.8(c)(4)RequirementsOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part. This subpart does not contain requirements for continuous opacity monitoring systems (COMS).
§ 63.8(c)(4)(i)CMS RequirementsNo. This subpart does not require COMS.
§ 63.8(c)(4)(ii)CMS requirementsYes.
§ 63.8(c)(5)COMS Minimum ProceduresNo. This subpart does not contain opacity or VE limits.
§ 63.8(c)(6)CMS RequirementsOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.8(c)(7)-(8)CMS RequirementsOnly for CEMS. Requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.8(d)(1)-(2)CMS Quality ControlOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.8(d)(3)Written procedures for CMSYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(d)(8).
§ 63.8(e)CMS Performance EvaluationSection 63.8(e)(6)(ii) does not apply because this subpart does not require COMS. Other sections apply only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.8(f)(1)-(5)Alternative Monitoring MethodYes, except you may also request approval using the precompliance report.
§ 63.8(f)(6)Alternative to Relative Accuracy TestOnly for CEMS.
§ 63.8(g)(1)-(4)Data ReductionOnly when using CEMS, except § 63.8(g)(2) does not apply because data reduction requirements for CEMS are specified in § 63.8000(d)(4)(iv).
The requirements for COMS do not apply because this subpart has no opacity or VE limits.
§ 63.8(g)(5)Data ReductionNo. Requirements for CEMS are specified in § 63.8000(d)(4). Requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.9(a)Notification RequirementsYes.
§ 63.9(b)(1)-(5)Initial NotificationsYes.
§ 63.9(c)Request for Compliance ExtensionYes.
§ 63.9(d)Notification of Special Compliance Requirements for New SourceYes.
§ 63.9(e)Notification of Performance TestYes.
§ 63.9(f)Notification of VE/Opacity TestNo. This subpart does not contain opacity or VE limits.
§ 63.9(g)Additional Notifications When Using CMSOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.9(h)(1)-(6)Notification of Compliance StatusYes, except this subpart has no opacity or VE limits, and § 63.9(h)(2) does not apply because § 63.8075(d) specifies the required contents and due date of the notification of compliance status report.
§ 63.9(i)Adjustment of Submittal DeadlinesYes.
§ 63.9(j)Change in previous informationYes, for change in major source status, otherwise § 63.8075(e)(8) specifies reporting requirements for process changes.
§ 63.9(k)Electronic reporting proceduresYes, as specified in § 63.9(j).
§ 63.10(a)Recordkeeping/ReportingYes.
§ 63.10(b)(1)Recordkeeping/ReportingYes.
§ 63.10(b)(2)(i)-(ii)Records related to SSMNo. Before the compliance date specified in § 63.7995(e), see § 63.998(c)(1)(ii)(D) through (G) and (d)(3) for recordkeeping requirements for periods of SSM. On and after the compliance date specified in § 63.7995(e), see § 63.8080(i).
§ 63.10(b)(2)(iii)Records related to maintenance of air pollution control equipmentYes.
§ 63.10(b)(2)(iv)-(v)Records related to SSMYes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
§ 63.10(b)(2)(vi), (x), and (xi)CMS RecordsOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.10(b)(2)(vii)-(ix)RecordsYes.
§ 63.10(b)(2)(xii)RecordsYes.
§ 63.10(b)(2)(xiii)RecordsYes.
§ 63.10(b)(2)(xiv)RecordsYes.
§ 63.10(b)(3)RecordsYes.
§ 63.10(c)(1)-(6), (9)-(14)RecordsOnly for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
§ 63.10(c)(7)-(8), (15)RecordsNo. Recordkeeping requirements are specified in § 63.8080.
§ 63.10(d)(1)General Reporting RequirementsYes.
§ 63.10(d)(2)Report of Performance Test ResultsYes.
§ 63.10(d)(3)Reporting Opacity or VE ObservationsNo. This subpart does not contain opacity or VE limits.
§ 63.10(d)(4)Progress ReportsYes.
§ 63.10(d)(5)(i)SSM ReportsNo. Before the compliance date specified in § 63.7995(e), see § 63.8075(e)(5) and (6) for the SSM reporting requirements. On and after the compliance date specified in § 63.7995(e), these requirements no longer apply.
§ 63.10(d)(5)(ii)Immediate SSM reportsNo.
§ 63.10(e)(1)-(2)Additional CMS ReportsOnly for CEMS, but § 63.10(e)(2)(ii) does not apply because this subpart does not require COMS.
§ 63.10(e)(3)ReportsNo. Reporting requirements are specified in § 63.8075.
§ 63.10(e)(3)(i)-(iii)ReportsNo. Reporting requirements are specified in § 63.8075.
§ 63.10(e)(3)(iv)-(v)Excess Emissions ReportsNo. Reporting requirements are specified in § 63.8075.
§ 63.10(e)(3)(vi-viii)Excess Emissions Report and Summary ReportNo. Reporting requirements are specified in § 63.8075.
§ 63.10(e)(4)Reporting COMS dataNo. This subpart does not contain opacity or VE limits.
§ 63.10(f)Waiver for Recordkeeping/ReportingYes.
§ 63.11Control and work practice requirementsYes.
§ 63.12DelegationYes.
§ 63.13AddressesYes.
§ 63.14Incorporation by ReferenceYes.
§ 63.15Availability of InformationYes.
[85 FR 49749, Aug. 14, 2020, as amended at 85 FR 73914, Nov. 19, 2020]
authority: 42 U.S.C. 7401
source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.